click here
Madurai - BODINAYAKKANUR ELECTRIFICATION WORKS COMPLETED (on 30 March 2024 itself)...
{MADURAI - BODINAYAKKANUR ELECTRIFIED SECTION INSPECTED
...
more...
Yesterday, Shri A.K. Siddhartha, Principal Chief Electrical Engineer (PCEE) of Southern Railway, led the statutory inspection of the newly electrified Madurai Junction - Bodinayakkanur Section spanning 90.41 km.
Starting from Madurai Junction at 09:30 hrs, the inspection journey covered various checkpoints including Road Over Bridge No.4 (Madurai outer), Level Crossing No.6, Sub sectioning Post at Usilampatti, OHE wiring over the railway bridge, and curvature assessments.
At Andipatti Railway station, the inspection delved into OHE arrangements beneath the Foot Over Bridge, along with assessing staff competency and the adequacy of maintenance tools and equipment for working in the electrified section.
The inspection concluded at Bodi at 14:20 hrs, with particular attention given to safety measures at the Power line crossing at Km 66.
Following the inspection, a speed trial was conducted using a train formation attached with an AC (Electric) Loco, starting from Teni at 17:53 hrs and arriving back at Madurai at 19:25 hrs.
Shri Sameer Dighe, Chief Project Director (CPD) of Railway Electrification, Chennai, along with Shri A. Sundaresan, Chief Electrical Distribution Engineer (CEDE), Shri Sandeep Kumar, Chief Signal and Telecommunications Engineer (Planning), Shri C. Selvam, Additional Divisional Railway Manager of Madurai Division, Shri M.S. Rohan, Deputy Chief Electrical Engineer of Railway Electrification, Madurai, and Shri S. Muthukumar, Divisional Electrical Engineer, Traction Distribution, accompanied the PCEE during the inspection and speed trial.}
UPDATE THE ATLAS @ADMIN @ATLASMONITOR
please wait...Translate to Englishclick here
Madurai - BODINAYAKKANUR ELECTRIFICATION WORKS DONE (on 30 March 2024)...
MADURAI - BODINAYAKKANUR ELECTRIFIED SECTION CHECKED
So, yesterday, A.K. Siddhartha, the main guy in charge of electrical stuff at Southern Railway, checked out the new electrified stretch from Madurai Junction to Bodinayakkanur, which is 90.41 km long.
They kicked off the inspection from Madurai Junction at 9:30 AM and hit up several spots like Road Over Bridge No.4 (Madurai outer), Level Crossing No.6, Sub sectioning Post at Usilampatti, OHE wiring on the railway bridge, and curved areas.
While at Andipatti station, they checked out the OHE setup under the Foot Over Bridge and made sure the staff was good to go and had the right tools for working in the electrified zone.
The inspection wrapped up at Bodi around 2:20 PM, paying close attention to safety at the Power line crossing at Km 66.
After that, they ran a speed test with a train pulled by an Electric Loco, leaving Teni at 5:53 PM and getting back to Madurai at 7:25 PM.
Shri Sameer Dighe, the Chief Project Director for Railway Electrification in Chennai, and a bunch of other important guys were with the PCEE during the check and speed test.
UPDATE THE ATLAS @ADMIN @ATLASMONITOR