Latest captures from New island platforms and station building construction site in Indore.
Summary of ongoing work :
1. BG line is completely laid towards one side of the island platform
2. Other...
more... side still need lot of ground work, partial line laid
3. Station building is 95% ready. Coloring finished. Marble and granite work under progress. Electrification and final touching remains.
4. Uprooting of old MG line and lying ballast and BG line towards Shastri Bridge has just begun.
5. Electric poles are the same. No new progress on this side.
After seeing the current pace of construction work and with lot of ground work still remaining on both ends of the island platforms and will INDM-MHOW MG line still operational, I have no doubt to say that it would take at least 6 months to completely finish the construction work and start trains from new platforms.