Sur-Dd: Doubling reached till Kurdiwadi(commencement is pending), work in under progress for remaining line from Kwv to Bgvn(Major bridges are here). Pune-Mrj-Ld: Parallel work of doubling/electrification is under progress for Pune-Mrj-Ld, till now none of the doubling patches has been commenced, only new bridge on river krishna near Kudachi is opened to traffic early this year.