Info Update on Doubling Works between Dhone Jn/DHNE - Pendekallu Jn/PDL and Gooty Jn/GY - Dharmavaram Jn/DMM sections.
Pic 1,2,3 and 4 - Display the progress of works between DHNE - PDL. Ground leveling work is in progress with some intermediate gaps due to hills, mounds and some waterways.
Pic 5 to 23 - Display the progress of works between GY - KLU. Ground leveling work is mostly done, sleepers and gravel has been stashed along side of track and the bridge work across the Penna River at KLU is almost done.
Pic...
more... 24 - Display the progress of construction of new platform at Zangalapalle/ZPL. New platform work at Prasannayana Palle/PSPY is also of the same status. (I'm sorry, couldn't take more pictures because of the Goods train)
Pic 25 to 28 - Display the progress of works between ZPL - DMM outskirts - except one or two bridges every stretch is as shown in the pics.
Pic 29 to 33 - Display the progress of works near DMM.
Pictures were taken on 28/07/2018.