track laying work left..work slow near near gdg entrance & kanaginahal station .
* gadag-annigeri most of work completed ..good news is that almost bridges construction completed track laying work left .
* annigere-hubballi -completed &opened .
+NOTE: good thing all stations btn HPT-UBL stations getting 2PF or 3 PF
#Hitnal,kanaginahal,hulikote,binkadtaddi all these stations 2PF under construction
#also SWR /hubballi div finally started giving importance to construct ROB/RUB which they were neglecting specially btn ubl -gdg section RUB taken at most places..
/RE work /Info
-OHE foundation work started from 140.0kms milestone from HPT side at HPT outskirts towards UBL side..
-OHE foundation can be seen upto bhanapura (102kms)
- few OHE poles can be seen for few kms before & after koppal.
-No OHE foundation can be seen btn bhanapura-hubballi except at annigere for 1km OHE foundation done.
/photos details/
1. OHE foundation at munirabad.
2.Hitnal station 2nd PF construction.
3.OHE poles before Koppal.
4. new ROB construction at koppal 85% work completed.
5.OHE poles after Koppal.
6.RUB construction near bhanapura.
7.kanaginahala 2nd PF construction .
8. OHE poles dumped at GDG.
9.new rob construction at GDG towards solapur line.
10. start point of GDG-HOTGI doubling.
11.OHE foundation just before Annigere.
12. doubling work at Annigere.
13.new ROB at UBL outer.
14.some construction going on ..dont know for what
15.16,&17 NEW PIT LINE CONSTRUCTION at HUBBALLI .
18. some construction going on ..dont know for what at coaches repair depot side beyond PF 5 .
THE END