Udaipur Ajmer #Electricfication 08/01/19 Update
1. Udaipur City foundation work pending outdur poles fixed to ranapratap nagar
2 ranapratapnagar to debari wireing work pending. Only tunnel side poles work not fix.. Almost 98!% complete.
3 debari to berach work complete... Only mejar work and sub station work due.
4...
more... Chanderia berach chittorgarh poles work 70% completely and wireing work due.
I think one month more this time section completely Electrify.