Actually got the update from ZRUCC member from Guntur. Now MPS also increased to 110 in Nallapadu-Nadikude section. Trials for MPS upgradation happened in Feb.
Currently Vishnupuram-Nalagonda electrification is left, which is expected to be completed by April end. Elocos to ply with freight from May onwards. Miryalaguda TSS work is in progress and Gurazala TSS work will start shortly.