DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 99% (As per latest update at STP and KB couple of poles and cross bars are pending)
Brackets - 73% done (Completion expected by Oct2019)
Wiring...
more... - Initiated on 31-Aug-2019 at MBP/Mohibullapur. From DAL/DaliGanj Junction wiring started leaving one patch for final linking with live wire. As per latest update wiring reached till BJLP however couple of patch's in between been left for later connection(Completion expected by Nov2019)
SSP - 3 SSP's been located however except foundation at BKT, SD and STP nothing much has completed (Completion expected by Nov2019 or Dec2019)
OHE wire energized - Expected by end of Nov2019 or starting of Dec2019
Trial run : Expected by 12-Nov-2019
CRS inspection - Expected by Dec2019
Commercial uses - Any point of time after successful CRS planned in Jan2020
** All provided dates are tentative**