Detailed construction progress Update for PF4 and PF5 at Muzaffarpur Jn.
As evident from the pics, almost 50% of civil work is done. Central FOB has been connected to the new platform, and other FOB is left out. A third new FOB is under construction as well, whose pillars have been laid down.
The remaining civil work is for PF shed construction. After that, passenger amenities such as benches, taps, lighting, fans, PA system will be installed.
Hopefully...
more... by end of this year, we might see these two new platforms being functional and ease out the PF congestion at MFP.
P.S. Sapt Kranti can be seen in the Pitlines, undergoing cleaning and Primary Maintenance.