Solapur Mohol new electrification work started,new doubling progress in Bhalwani Bhigwan Solapur Div
n the video, new updates have seen across previous videos, lets check
1. Solapur Bale : New foundation work has started.
2....
more... Bale Pakni : Wiring ( except near bridge ) is completed.
3. Pakni Mundhewadi : Wiring is completed ( except bridge )
4. Mundhewadi Mohol : Foundation work is seen near Mundhewadi section ( previously which was not even seen ) & new poles installed
5. Bhalwani Jeur : Already doubled + electrified
6. Jeur Pophlaj : New platform work going on at Jeur
7. Pophlaj Washimbe : Doubled & Electrified
8. Washimbe Parewadi : Bhopal Peth bridge new girders & alignment
9. Parewadi Jinti Road : Hingni bridge aligned & work in progress of doubling
10. Jinti Road Bhigwan : Stones laid and sleepers placed at some places