- 78.70 km
➡️Length commissioned - 34.59 km
➡️Remaining - 44.11 km
➡️Overall Physical Progress - (3rd line-72%) (4th line-70%)
🪙 Cost - 1177.97 Cr
🪙 Expenditure till date - 1035.92 Cr
🟩Completed doubling - 34.59 km (43.95%)
A) Khapri - Sindi
🟩Near completion section- 27.14 km (34.48%)
B) Sindi - Seloo Road
C) Khapri - Ajni
🟩In Progress section- 16.99 km (21.58%)
Seloo Road - Wardha
Ajni - Nagpur
➡️Land acquisition- 36.47/36.51 Ha (99.50%)
➡️Completed works details -
➡️Earthwork - 22.39/32.63 Lcum(69%)
➡️Important Bridges - 2/2 (100%)
➡️Major Bridges - 10/12 (83%)
➡️Minor Bridges - 70/144 (51%)
➡️Station building - 2/7 ( 28%)
➡️Track linking - 70/157 km (44%)
➡️OHE (Overhead equipment) Foundation- 1010/4048 (25%)
➡️OHE Mast erections - 890/3680 (24%)
➡️OHE Wiring Tkm- 45/184 (25%)
➡️New Signalling Electronic Overlocking - 6/20 Stations (30%)
➡️Signalling Indoor and Outdoor works - 6/20 (30%)
🟩Completion of Wardha - Nagpur section 3th/4th lines will help to increase train mobility and will reduce congestion of section.