#CRupdate on Special Block for Infra upgrade work at Thane station.
HISTORIC WORK ON WIDENING OF THANE STATION's PLATFORM 5/6 COMPLETED!
...
more...
• Widening of Platform 5/6 by 2-3 meters for 587 meters length
• Use of 750 pre-cast hollow blocks
• Coordination of 400 laborers, 20 teams, and 10 contractors
• Minimal disruption despite 935 train cancellations Efficient execution with zero delays!
• Work carried out along with NI work of CSMT, one of the busiest coaching terminals of Indian Railways.
* Deep appreciation to the work force for their meticulous planning, precision at work and timely execution.