Project Schedule of RCF Rae Bareli till Date:
1.Construction of Phase-I work: Furnishing and Finishing group of shops, temporary office and storage space, temporary accommodation and logistics support including specified M&P, T&P and embedded track, supporting electrical installation. #TARGET DATE OF COMPLETION: March’ 11 #STATUS: Work Completed
2.Construction of Phase-II & III work: Shell assembly Shop, Bogie Shop, Wheel Shop, Paint Shop, Machine Shop with full M&P, T&P and Stores with logistic Support. Administrative building, Technical Training Center, Hostel, Township - Housing, Service buildings, Shopping complex & Sports complex etc.#TARGET...
more... DATE OF COMPLETION: Dec’ 14
#STATUS: Work in Progress