यात्री ट्रेन सुविधाओं में शीघ्र इजाफे की उम्मीदThe doubling of the 465 km railway line between Katni and Garhwa, started in 2016-17, is over 80% complete (358 km). Railway officials anticipate completion of the remaining work within six months. The electrification and doubling will benefit the region by providing more passenger train services. Doubling efforts...
more... are facing challenges. The 78 km doubling in the Singrauli-Katni section is delayed due to the Sanjay Tiger Reserve. The National Board of Wildlife is yet to approve the required forest clearance. Railway Board has completed a final location survey for an alternative alignment. The project's DPR is being prepared for speedy completion. Of the 261 km doubling in the region, 211.36 km is complete. West Central Railway's Chief Public Relations Officer confirmed that 11.90 km between Khanna Banjari and Mahroi, 28.65 km between Niwas Road and Saraiagram, and 19.10 km between Mahroi and Vijay Sotan were completed by December. The 63 km doubling between Singrauli and Chopan is stalled due to the construction of a bridge at the Rihand railway bridge near the Obra Dam. Out of the 141 km between Chopan and Garhwa Road, 23 km has been impacted by the need to build bridges, with completion expected by March. The 32 km doubling between Shaktinagar and Karaila Road is almost complete. However, the 10 km doubling between Anpara and Krishnashilla is stalled in court due to compensation issues for those displaced near the Anpara bridge.
Katni aur Garhwa ke beech 465 km railway line ka doubling 2016-17 mein shuru hua tha aur 80% (358 km) se zyada kaam pura ho chuka hai. Rail officers ka kehna hai ki baki kaam bhi chhe mahine mein pura ho jayega. Electricified doubling se yaha ke logo ko bahut saare...
more... important passenger train services milenge. Doubling mein kuchh problems bhi aa rahi hain. Singrauli-Katni section mein 78 km ka doubling Sanjay Tiger Reserve ki wajah se ruk gaya hai. National Board of Wildlife se forest clearance ka maamla pendinge hai. Railway Board ne ek alternative alignment ka final location survey complete kar liya hai. Project ka DPR banaya ja raha hai aur kaam jaldi complete karne ki koshish ki ja rahi hai. Is region mein 261 km doubling mein se 211.36 km pura ho chuka hai. West Central Railway ke Chief Public Relations Officer ne confirm kiya hai ki Khanna Banjari aur Mahroi ke beech 11.90 km, Niwas Road aur Saraiagram ke beech 28.65 km aur Mahroi aur Vijay Sotan ke beech 19.10 km ka kaam December tak pura ho chuka tha. Singrauli aur Chopan ke beech 63 km doubling Obra Dam ke paas Rihand railway bridge par bridge banane ki wajah se ruk gaya hai. Chopan aur Garhwa Road ke beech 141 km mein se 23 km mein kuchh bridges banane hain aur officers ka kehna hai ki ye kaam March tak pura ho jayega. Shaktinagar aur Karaila Road ke beech 32 km doubling almost complete ho chuka hai. Lekin Anpara aur Krishnashilla ke beech 10 km doubling Anpara bridge ke paas displacement ki wajah se court mein pendinge hai.