Three firms bid for ₹4,132 crore construction contract for Mumbai Metro Line 12Mumbai's Metro Line-12, the 22.17 km Orange Line connecting Kalyan, Dombivali, and Amandoot (Taloja), has attracted bids from three prominent firms for civil construction. This elevated extension, with 19 stations, is a crucial addition to Line-5 and will cost Rs 4,132 crore. After a revised bidding process, the final contract, Package...
more... CA-240, includes two additional stations and a 30-month completion deadline. The selected contractor will be responsible for designing and constructing the viaduct and stations, including strategically positioned stops like Ganesh Nagar, Dombivli MIDC, and Turbhe. The technical evaluation of bids is underway, followed by financial bid opening to determine the lowest bidder. Upon completion, Line-12 will be the longest EPC package in India's metro construction, exceeding the current record held by Bangalore Metro's Package 3. This development is anticipated to transform Mumbai's commuting landscape.
Mumbai ka Metro Line-12, jo ki 22.17 km ka Orange Line hai aur Kalyan, Dombivali aur Amandoot (Taloja) ko connect karega, ke liye civil construction ke liye teen prominent firms ne bids submit ki hain. Yeh elevated extension, jisme 19 stations hain, Line-5 ka ek important addition hai aur iski cost...
more... Rs 4,132 crore hai. Revised bidding process ke baad, final contract, Package CA-240, mein do additional stations aur 30-month completion deadline hai. Selected contractor ko viaduct aur stations ko design aur construct karna hoga, jisme strategically positioned stops jaise Ganesh Nagar, Dombivli MIDC aur Turbhe bhi include hain. Technical evaluation of bids chal raha hai, uske baad financial bid opening hoga jisse lowest bidder ka pata chalega. Completion ke baad, Line-12 India ke metro construction mein sabse lamba EPC package hoga, jiska current record Bangalore Metro ke Package 3 ke paas hai. This development Mumbai ke commuting landscape ko transform karne ki ummeed hai.