भीरपुर आरओबी का बीम लांच, निर्माण कार्य ने पकड़ी गतिThe construction of the Bheerpur ROB, being built in anticipation of the Maha Kumbh, has progressed significantly. The Setu Nigam launched the beam on the first day of the road closure, allowing construction to accelerate. The ROB is in its final phase, with the topmost portion's beam launch being completed after...
more... a three-day road closure from March 1st to 3rd. The Setu Nigam team worked overnight to complete the beam launch. The Project Manager, Anirudh Kumar, acknowledged the challenging nature of the task due to traffic disruption. With the beam launch, construction is expected to move quickly, and the Bampore ROB beam launch is scheduled to happen soon.
Maha Kumbh ke liye ban raha Bheerpur ROB ka kaam aage badh gaya hai. Sethu Nigam ne block ke pehle hi din beam launch kar diya. Ab construction kaam jaldi hoga. Bheerpur ROB ka kaam last stage mein hai. Top portion ka beam launch karne ke liye, Setu Nigam ne 1st...
more... March se 3rd March tak block liya tha. Team ne raat bhar kaam karke beam launch kar diya. Setu Nigam ke Project Manager, Anirudh Kumar ne bataya ki yeh bahut tough kaam tha, aur traffic block se logon ko pareshani hui. Ab construction jaldi hoga, aur Bampore ROB ka beam bhi jaldi launch hoga.