सिरमटोली रेलवे फ्लाईओवर ब्लॉक के लिए रेलवे कर रही समीक्षा, दक्षिण पूर्व रेलवे भेजी जायेगी रिपोर्टThe construction of the Sirmatolie Mekan flyover in Ranchi is 60% complete. To finish the project, a railway block is required near Sirmatolie. The construction company, L&T, is working with the Ranchi Railway Division and the Road Construction Department to obtain this block. L&T has requested 119 hours of block...
more... time, spread across various days in four-hour intervals. The railway officials are reviewing this request and have provided a format for L&T to fill out, detailing their block requirements and how the railway should prepare. After reviewing this information, the railway will send a report to the South Eastern Railway for approval before proceeding further. The flyover, which is estimated to cost ₹337 crores, is being built over the railway crossing between Nivaranpur and Patel Chowk. The Minister of Road Construction, Bansat Soreen, visited the site and instructed L&T to complete the project by September. Over 100 trains pass through Ranchi and Hatia railway stations daily, including passenger, express, and freight trains. Therefore, a railway block would significantly impact train operations, requiring careful planning and preparation.
Ranchi mein Sirmatolie Mekan flyover ka kaam 60% complete ho chuka hai. Iska kaam pura karne ke liye Sirmatolie ke paas railway block lene ki jarurat hai. Flyover banane wali company, L&T, iske liye Ranchi Railway Division aur Path Nirman Vibhag ke saath mil kar kaam kar rahi hai. L&T ne...
more... pehle hi railway se 119 ghante block lene ki maang ki hai. Yeh block alag-alag dino mein char-char ghante kar lene ki maang ki gayi hai. Railway officials is request ko review kar rahe hain aur unhone L&T ko ek format diya hai. Isme company ko apne block requirements aur railway ko kya taiyari karni hai, yeh likhna hoga. Is information ko review karne ke baad railway yeh report South Eastern Railway ko approval ke liye bhejega. Flyover, jiski estimated cost ₹337 crores hai, Nivaranpur aur Patel Chowk ke beech railway crossing ke upar bana hai. Road Construction Minister, Bansat Soreen, ne site ka inspection kiya aur L&T ko September tak kaam complete karne ka order diya. Ranchi aur Hatia railway station se har din 100 se zyada trains guzarti hain, jinme passenger, express, aur freight trains shamil hain. Isliye railway block se train operations par bahut bada impact padega, aur iske liye bahut careful planning aur taiyari karni padegi.