Panipat News: तीन साल से बंद पड़े मनाना फाटक पर रेलवे ओवरब्रिज का निर्माण कार्य फिर शुरूThe construction of the railway overbridge (ROB) at Manana railway crossing in Samalkha, which was halted for three years, has resumed on Tuesday. The construction, undertaken by the Railways and Haryana Public Works Department (PWD), began in 2019. The ROB, costing ₹17.5 crore, was stalled due to land acquisition issues for...
more... the service road. However, the Deputy Commissioner intervened and reached an agreement with the farmers, allowing the construction to resume. The SDO of the PWD department, Shailendra Bhatia, initiated foundation digging for the walls and aims to make the overbridge accessible within the next three months. The ROB, along with the service road, is intended to benefit residents of 13-14 villages situated across the railway line.
Samalkha mein Manana railway crossing pe ban raha railway overbridge (ROB) ka construction, jo teen saal se rukha hua tha, Mangalwar ko fir se start ho gaya hai. Yeh construction, Railway aur Haryana Public Works Department (PWD) dwara kiya ja raha hai, 2019 mein shuru hua tha. ₹17.5...
more... crore ka yeh ROB, service road ke liye land acquisition ke issue ki wajah se last teen saal se band tha. Lekin, Deputy Commissioner ne intervene kiya aur farmers se agreement kar liya, jisse construction resume ho paya. PWD department ke SDO, Shailendra Bhatia ne walls ke liye foundation digging ka kaam start karwaya hai aur unka aim agle teen mahine mein overbridge ko access karne layak bana dena hai. Yeh ROB, service road ke saath, railway line ke paar basne waale 13-14 gaon ke residents ko benefit dega.