Gwalior Sheopur GC Project update -
Jora Alapur . (JPO)
1. The work of laying railway track is going on fast
in
...
more... Jora Alapur.
2. The building of Jora Alapur Railway Station
(JPO)is 70% complete and the platform is also
80%.
3. Tracks are being laid at some places and along
with this the work of electrification is also going
on.
4. Some railway equipments have also been
installed inside the building of the railway station,
such as signal management equipment,
telephones for communication, etc.
PC:-Udata Kabutar Official.
please wait...Translate to EnglishYo, here's the update on the Gwalior Sheopur GC Project -
Jora Alapur. (JPO)
1. They're making good progress on laying the train tracks in Jora Alapur.
2. The Jora Alapur Railway Station (JPO) building is about 70% done, and the platform is almost 80%.
3. They're also laying tracks in some areas and working on electrification.
4. The station building has been equipped with stuff like signal management and communication phones.
PC: Udata Kabutar Official.
please wait...Translate to HindiGwalior Sheopur GC Project update -
Jora Alapur . (JPO)
1. Jora Alapur mein railway track ki kaam tez chal rahi hai.
2. Jora Alapur Railway Station (JPO) ka building 70% complete hai aur platform bhi 80%.
3. Kuch jagah par track lag rahi hai aur iske saath hi electrification ki kaam bhi ho rahi hai.
4. Railway station ke building ke andar kuch railway equipments bhi install kiye gaye hain, jaise signal management equipment, communication ke liye telephone, etc.
PC:-Udata Kabutar Official.