Sabarmati platform and other intermidiate location .
.
* Sabarmati - Kali road
New Broad Gauge Track laying started at some location
Electric poles have been fixed .. but Bracket tube and Stay tube has not installed .. yet
.
*Kali Road - Chandkheda
Laying of Sleeper completed , Tracks not camed on sleeper ,
Electrification poles installed
.
* Chandkheda - Khodiyar
Track laying done completely except At Level crossing not done .
electrification foundation work done. poles have not fitted yet .
.
* Khodiyar - Saij Serta Rd
Sleeper Layout work in progress,
Track laying also done at some location .
at few locations Ground levelling done .
no sign of Electrification ..
.
* Saij serta Rd - KaloL .
New Broad Gauge bridge construction not started
old MG sleeper not removed yet,
en- route and also at Kalol station ..
no sign of Electrification ..
Only MG track removal done. .
.
* KaloL - Jhulasan
Old MG sleeper and track removal done .
Ground levelling for BG not started .
Electrification poles have been installed .
Ground levelling for WDFC done .
.
* Jhulasan - Ghumasan
Old MG sleeper and track removal done .
Ground levelling for BG not started .
at few location .
at some location New Broad Gauge Track laying done . near Ghumasan station
no sign of Electrification .
WDFC ground levelling and bridge construction work in progress .
~ No loop creation will be done at Ghumasan
.
*Ghumasan - Dangarwa
BG Track laying done completely.. except level crossing
.
* Dangarwa - Jagudan
Old MG track and slepper removal done .
New BG sleeper can be seen at station
Ground Levelling not started at Dangarwa station .
post Dangarwa BG Track laying started ..
at few location. Sleeper arrangments done .and further sleeper laying work in progress
sleeper have been put on the site , laying is going on.
No sign of Electrification
.
*Jagudan - Mahesana
Completed Old MG track & sleeper removal done , no sign of Electrification .
Ground leveling for BG not started , no BG sleeper can be seen in this patch .
.
* At Mahesana station and outer .
New BG track laying started and sleeper laying for further Track work in progress
.
.
#AhmedabadAjmerDoubling#AhmedabadDelhiElectrification