in year 2008 both RTM-knw AKL & adi -udz GC projects were sectioned
still adi -udz section not in real pace after 6 years
still following sections are pending after section in RB
bhuj naliya 100 km (section in 2008)
Mehsana...
more... tarnga hill 46km(2011)
Miyagam karjan Smalya 100 km (2011)
Shapur Saradiya 46 km (2011)
Adi Btd 170 km (2012)
Jtl -das 100 km (2012)
no pogress on all section , main ADi-udz section me 5% pogress nahi he