Live pictures from new Indore Railway Station.
Highlights:
- Station building is 80% completed. One staircase is completed while a second is under construction.
- BG sleepers have been laid on the main line side while the other side is still not ready for it.
-...
more... A modern concrete mixing machine can be seen on site
- Some LED poles have been installed on the platform
- Couple of electric poles have been brought on to the platform. May be they are going the electrify the island platforms with the ongoing work
- Old MG line coming from LMNR side has been converted between Rajkumar ROB and the new station building area, while there is still no signs of conversion between LMNR and Rajkumar ROB
- I took some pictures from the first floor of station building, it was a beautiful view from there
Conclusion:
From my analysis, I can say that it will take 6 or more months to complete the whole work. They cannot start even a single side of new platforms until the station building is ready to serve the passengers.