Current Status : CASE CLOSED
Date of Action : 19 Aug 2015
Details : 1. Ajmer-Kota new line project:- The work is not started. Date of completion is not fixed. 2.Merta- Pushkar new line:- The work is not yet started. Date of compkletion is not fixed. 3. Ajmer-Swai madhopur yia Tonk new lineproject.;- The work is not started. Date of completion is not fixed. 4. Dausa- Gangapurcity new line project:- The date of completion is not fixed. 5. Ajmer -Palanpur doubling:- Work is being done in different phases by RVNL and NWR construction. The worl of Keshavganj-Swarupganj doubling completed...
more... and commissioned on 16.4.2015. The work in other section is in progress. Date of completion is not decided. Phulera-Degana doubling:- Date of completion is not fixed. 7 Jaipur-ChuruG.C.work:- Date of completion is not fixed.