***Electrification Status Of Pune -Daund & Daund -Manmad section as on 26.11.2015***
1)Pune-Daund Section -->
*Pune-GIT Yard-Double Electrified
*GIT yard To Hadapsar outer- only poles (no wires)
*Hadapsar To Daund Jn Outer -poles +...
more... wires installed (Double Electrified)
*Daund Jn outer To Daund Jn-only poles (no wires)
*By March 2016, Indian Railways will complete the electrification of this track till Bhigwan...
2)Daund-Manmad Section-->
*Daund Jn To Daund Marshalling Yard-only poles (no wires)
* From Daund Marshalling Yard To Sainagar Shirdi/ Manmad- Almost Completed..
*Manmad-Puntamba-Sainagar Shirdi section has been commissioned with 25 KV AC Traction on 11.8.2014
*Manmad-Sarola section has been commissioned with 25 KV AC Traction on 15.9.2015.
*Trains are running with electric locos between MMR to SNSI...e.g- Kalka,Puri express...
*Goods Trains are running with electric locos between MMR to Sarola..
***Target date for completion of work is 31.03.2016***