At present Udhna Jn. to Chalthan is single line-11.11 kms
Chalthan to Nandurbar(including) is double line -145.2 kms
Nandurbar to Hol single line -61.61 kms
Hol to Amalner double line(shortly to be commissioned)33.6 kms
Amalner...
more... to Paldhi double line 43.69 kms
Paldhi to Jalgaon single line 11.72 kms
So at present out of 306.93 kms to Jalgaon Jn from Udhna Jn.11.11+61.61+11.72= 84.44 Kms is pending.
Civil and Electrification work is progressing at acceptable pace and as per physical observations,it is likely that except for Chalthan Udhna section,rest all sections including Paldhi Jalgaon will be commissioned by 2018.