GUNTAKAL -HOSAPETE DOUBLE ELECTRIFICATION Update Part -1 (A.P/SCR)
1. GTL -towards BAY
2.&3GTL by pass only electric poles r fixed , wiring not done
4.GTL west - till here only erected electric poles can be seen but wiring not done ..also there is new substation under construction btn gtl-gtl west left side (unable to capture pic)
5.&6after...
more... GTL west fully electrified .
7.banatahal station - fully electrified .
8. after banatahal station - fully electrified near bridge.
9.near bevinahal station -fully electrified
10.after bevinahal station -fully electrified
11. karnataka- andhra border (a.p ends here)
wait for part -2 (karnataka/scr) ..SORRY for low videos/photo clarity captured during 6am so.