Progress update of #PuneMetro Reach-1 - PCMC-Range Hills
⏺️Total 237 segments are launched for viaduct
⏺️148 pillars with 69 pier caps are completed
⏺️188 footings are done & excavation in progress
⏺️Also, pillar foundation...
more... work is in progress at Nashik Phata