Hosapete - Hubballi double Electrification work update:
Almost 30 kms OHE PIT Holes work completed btn hitnal -bhanapur (133km -103km ) along ubl -hpt section (except at GIN due to station remodeling work going on) ..
1&2.pit hole work started from Hitnal station itself pic after hitnal ..
3.new ROB at KBL.
4&5.OHE...
more... pit hole work at Koppal PF
6. after KBL
after bhanapur OHE pit hole work yet to start.speed of
this project looks like going at fast rate.unlike hpt - gtl Electrification.
i saw huge no of electrical poles were dumped beside gadag pf.
Hosapete - Hubballi doubling work update:
*CRS for double line btn hosapete - koppal is on 16th & 17 nov.
*not much progress at gadag outer very slow work going on.. 4 bridges work also slow work towards HPT sides minimum 4-6 months required to completed doubling work btn gdg -hpt
*one ROB construction going near diversion of UBL/SUR lines at gdg.
* one cabin under construction at UBL outer for new BY pass line.
by 2019 dec likely to complete hpt -ubl doubling.