#PuneSolapurDoubling
While traveling in 16352 Nagarcoil - Tirupati - Mumbai Express, I have observed following progress of doubling.
Wadshinge - Interlocking work for UP main line is already completed new signals are ready for functioning.
Kurduwadi - Wadshinge to Kurduwadi outer track laid long back. Now the progress is KWV outer to KWV Junction new tracks are laid.
Major...
more... interlocking work is yet to be done, but all necessary tracks are laid.
So after doubling, line passing from PF 2 of KWV will be treated as UP Main line.
At present this line goes towards PVR/MRJ, therefore new track laid from KWV LC to KWV Pune end outer at extreme left side.
So this new line will goes towards PVR/MRJ after interlocking and existing PVR/MRJ line will be connected to new line towards Dhavlas from KWV outer. Here also new signaling system is installed and ready for testing.
(At present, construction of new platform beside PF 1 for 24 coaches trains will not be happening, so they will use PF 3 & 4 as usual).
Dhavlas - Construction of new platform is 80% completed. Tracks already laid in entire stretch.
Only interlocking work is remaining.
Kem - Bridge work at Kem outer is completed and PF 1 is closed for constructing new up main line adjucent to it.
Bhalawani - Here also platform work is 80% completed. Entire stretch from Wadshinge is ready for CRS after interlocking work.
After Bhalawani I haven't seen much progress, only leveling work is going on.