#PuneSolapurGulbargaDoubling
Bhigwan to Jeur - leveling work is in progress. RVNL will take another 5 years for this stretch.
Jeur to Bhalwani - 70% tracks laid and construction of platform at Jeur is in progress.
Bhalawani to Wadshinge - All the tracks are laid, signals are installed, construction of new platforms at Bhalawani, Kem, Dhavlas & Wadshinge are completed. Only interlocking...
more... work is remaining.
Wadshinge to Boroti - Line doubled.
Boroti to Dhudhani - 90 % tracks laid, new platforms constructed at Boroti & Dhudhani. Currently TSR given on this section to complete bridge over Seena river. Due TSR section clearance time increased by 15 mins.
Dhudhani to Kulali - 75% tracks laid and remaining work is in progress. Platform at Kulali is also constructed.
Kulali to Sawalagi - Leveling is progress, only few tracks laid. Construction of new platforms are in progress.
Sawalagi to Gulbarga - 97% work is completed along with construction of new platforms, installations of signals, interlocking work. Only part remaining was 200 m patch at Gulbarga due to ROB.
Now ROB at Jewargi Road is dismantled for track part only and leveling also done. Expected to complete this work within a month.
So hopefully, Gulbarga - Sawalagi, Dudhani - Boroti & Wadshinge - Bhalawani section should be commissioned asap.
Some of the stations like Kem, Bablad are partially closed for crossing trains are detained at nearest stations for 30-45 mins.
As seeing speed of work by RVNL, Jeur - Bhigwan section will take another 5 years as large bridges need to construct between each stations due to Ujani Dam backwater and Bhima River.