Length Commissioned up to Mar 2019 = 96.95 Km out of 182.23 Km. Target 2019-20 : 59.58 Km Work is in progress. 42.85 Km track linked. Work also is in progress in balance section. Expected Completion for entire section: 2021-22 (Subject to construction of 2 NO. of ROB on NHAI on both the apprach. of Malya-Miyanya Station.)