11060 Chhapra-Ltt Express waiting for signal at Phaphamau Junction Plt-2 today, on 23.11.2019. A new Platform (Platform No. 4) being constructed at phaphamau towards east side of stn in connection with prayag-phaphamau doubling.
Prayag-Phaphamau double line will not be ready by december due to this work and electrification work. Electric poles erection work just has started near Prayag north side. Leaving this Platform and more 400 metres to its south, at remaining full stretch between prayag and phaphamau, sleepers placed fully and at most places track also laid by tightening with sleepers using iron clips.
At...
more... other places also, tracks has kept on laid sleepers.