#ElectrificationUpdate #16December2019
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 100%
Wiring - 100%
OHE...
more... van - Completed entire section
SSP (2 as on date) - At STP/Sitapur Junction 80% work has been completed (Completion expected by Dec2019). At SD/Sidhauli 75% work has been completed (Completion expected by Dec2019 or so).
SP (Only 1) - Basic structure completed and two transformer has been placed at BKT/Bakshi Ka Talab (Completion expected by 2020).
Block - Completed and new line has been connecetd with existing line at STP/Sitapur Junction and DAL/DaliGanj Junction as well.
OHE wire energizing - From 10-Dec-2019 wire has been energized.
Trial run : First trial run expected on 20-Dec-2019 instead of 22-Dec-2019. More information awaits.
CRS inspection - As per newspaper 26-Dec-2019
Commercial uses - Any point of time after successful CRS and permission granted by traffic department.