Presenting few pics and updates from one of the most awaiting ongoing project of NER - IR..
Tarighat-Ghazipur -(Mau) rail line with rail cum road bridge...
ECR is doing electrification of Tarighat line while bridge work is in process... Pillars done, fabrication work in progress, Singla Co doing this project and currently speed of work is very low may just bcoz of now enthrone has finished i mean Sinha Ji effect...
Special...
more... Thanks to one of my RF cum Friend Raj Soni of Ghazipur who help me to get their with his bike ride..
We reach the lands end of Tarighat Station and saw Bridge work from very close location...
It will take 2-3 years to complete this project till Ghazipur..
I found tarighat as very much peaceful place for Relaxing...
Enjoy the pics and updates..