Adi - HMT - Dnrp tak complete ho gaya he
Or Kharwa Chanda to Udaipur complete ho gaya he
Ab 92 Km ka CRS baki he ...jisme 17km tak track dal diya gaya he or ab 75 km track dalna baki he .... tunnels ka finishing ka kam almost complete he ...oda Bridge par girders rakne ka kam baki he