TT might be workable provided CR is willing to keep a pf turnaround at DR which has just 2 PF for originating & terminating trains. Also in UBL is 4.5 hours sufficient for PM at UBL end ? Train ideally in most cases takes at least 40-45 min before it is shunted from PF to pit line