Mhow Sanawad GC is not started yet. It has been divided into 2 part, Mhow Muktiyar, n Muktiyar Sanawad.
Mhow Muktiyar section, WR is doing FLS, but FLS is failed as working agency left the work, so it needs to re-start by tender process.
Muktiyar...
more... Sanawad Section, some private land acquisition going on to shift Omkareshwar railway station, also new Narmada River bridge needs to be built.
Also khandwa Jn to Khandwa bypass Cabin, 4.5KM GC is going on, will complete in this year.
Khandwa railway station platform work is started now.
So only paper work is going on, nothing field work. Ratlam division loves to keep run Mhow Omkareshwar MG passenger.
Khandwa to Almakhurd field work in going on.
Almakhurd to Akot - land acquisition issue due to forest. Not solved yet.