🪙Cost- ₹ 1384.72 Cr.
🪙Expenditure till date- ₹ 811.70 Cr.
➡️Overall Physical Progress- 56%
➡️Length-132.34 km
➡️Length commissioned- 33.33 km (25%)
➡️Remaining- 101.49 km
➡️Land acquisition completed- 125.52/136.44 Hectare (92%)
A) Completed Sections : 33.33 km (25.18%)-
➡️Wardha- Hinganghat
B) Near Completion Sections- 47.98 km
(Target- 2023-24) (36.25%)
➡️Hingaghat-Chikni- 28.65 km
➡️Majri-Tadali- 19.33 km
C) In Progress Sections - 51.03 km (38.57%)-
➡️Chikni Road-Majri- 22.50 km
➡️Tadali-Ballarshah- 28.53 km
D) In Progress Rail-over Rail Bridge (ROR)-
➡️Wardha-Sewagram
➡️At Majri & at Tadali
🟩Completed Works-
➡️Earthwork- 15.16/25.81 Lcum (58%)
➡️Blanketing- 60000/195000 Lcum (30%)
➡️Important Bridges- 1/2 (50%)
➡️Major Bridge- 6 in progress out of 12.
➡️Minor Bridge/RUB- 21/146 (15%)
➡️Station Building- 5/19 (26%)
➡️Track linking- 30/132 (23%)
➡️Overhead Equipment OHE Foundations- 620/2904 (22%)
➡️OHE Mast Erections- 368/2640 (14%)
➡️OHE Wiring Track km- 15/132 (11%)
➡️Signalling Electronic Interlocking- 3/18 (16%)
➡️Signalling indoor and outdoor works- 3/18 (16%)
Completion of this new 3rd line will reduce congestion of this Secunderabad- Nagpur busy route and will improve mobility of the trains.
🟩Progress of doubling/3rd/4th lines all over Central Railway 5 divisions-
➡️CR has completed 147.77 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023
➡️3886.95 Crs planned by Cr in this year for new lines/doubling/3rd/4th line.
➡️2983.47 Crs expenditure till date