💰 Cost- ₹ 792.89 Cr.
💰 Expenditure till date- ₹ 641.33 Cr.
🟢Overall Physical Progress- 50%
🔘Length- 67.35 Km.
🔘Land acquisition completed- 35.96 / 49.23 Hectare (73.04%)
🟢In Progress Works-
☑Earthwork - 9.11 /24.04 Lcum (38%)
☑Blanketing - 2.26 Lcum in progress
☑Major Bridge - 5 In Progress out of 8 Bridges
☑Minor Bridge/RUB- 23/203 (11%)
☑Road over bridge (ROB) - 2 In Progress
☑Station Building- 3/35 (9%)
☑Overhead Equipment OHE Foundations- 200/1400 (15%)
☑OHE Mast Erections- 170/1200 (14%)
🔴Completion of this new 3rd line will reduce congestion of busy Kalyan - Kasara Suburban and mail express route and will improve mobility of the trains.
🔘Progress of doubling/3rd/4th new lines all over Central Railway’s 5 divisions-
🔘CR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date.