#Admin #Moderator Source Cr X Handle
#CRInfraUpdates
ЁЯЯйDevelopment of Ajni Station as satellite terminal with construction of 2 new platforms and 2 looplines of 26 coach length
ЁЯТ░Cost-45.33...
more... Crores
тЬЕ Overall Physical progress-30% completed.
A) Scope of work-
ЁЯФШConstruction of 2 new platforms
ЁЯФШConstruction of 2 new looplines
ЁЯФШConstruction of 4 new stabling lines with secondary coach maintenance facility
ЁЯФШConstruction of 1 new Pit line for train examination
ЁЯФШConstruction of service buildings for mechanical works
ЁЯФШConstruction of Cover over shed of 500 meter on platform
ЁЯФШConstruction of coach water facility
ЁЯФШConstruction of 2 new FOBs (Foot over bridges) for connecting new proposed platforms.
B) Completed works-
ЁЯФШAll contracts awarded for construction of all civil works, new platforms, covershed on platforms, washing pit lines, stabling lines, coach watering pathway, service buildings
ЁЯФШAll service buildings such as mechanical work completed
ЁЯФШWashing pit line of 585 meter construction completed. Track linking in progress.
ЁЯФШTrack linking of 4 stabling lines completed
ЁЯФШOHE (OverHead Equipment) & Electrical tenders awarded.
ЁЯФШSignalling & telecom infringement obstruction removal work in progress.
ЁЯФ┤Completion of these project new platforms will improve mobility of trains in Nagpur area and will reduce congestion.