Expenditure till date- ₹ 1051.49 Cr.
🟢Overall Physical Progress- 40%
🔘 Total Length- 297.05 Km
🔘 Length commissioned - 93.95 Km
🔘Remaining- 203.1 km
🔘Land acquisition completed- 77.29 / 99.25 Hectare (76.84%)
A) Completed Sections: 93.95 Km (31.62%)
🔘Kohli- Chichonda
B) Near Completion Sections- 11.68 km (3.93%)
🔘Kohli- Kalmeshwar
C) In Progress Sections- 191.42 km (64.44%)
🔘Chichonda – Itarsi
🔘Nagpur – Kalmeshwar
🟢Completed Works-
☑Earthwork including Blanketing 46.65/103 Lcum (45%)
☑Important Bridges- 3 in Progress
☑Major Bridge + Rail Over Rail Bridge- 12/34 (36%)
☑Minor Bridge/RUB- 91/382 (24%)
☑Station Building- 9/30 (30%)
☑Track linking- 85/280 Track km (30%)
☑Overhead Equipment OHE Foundations- 1066/6666 (16%)
☑OHE Mast Erections- 970/6060 (8%)
☑OHE Wiring Track km- 50/280 (17%)
🔴Completion of this new 3rd line will reduce congestion of Nagpur – Itarsi – Bhopal busy route and will improve mobility of the trains.