Shravasti News: खलीलाबाद-श्रावस्ती-बलरामपुर नई रेल लाइन को विशेष प्रोजेक्ट का दर्जाThe construction of the second phase of the Khalilabad-Bahraich via Shravasti rail line is scheduled to begin in the new year. The first phase involves land acquisition. The government has declared this phase as a special project, ensuring sufficient funding. The entire project is divided into two phases. The first phase,...
more... covering Khalilabad to Bansi, has almost completed land acquisition. Work on stone blasting and earthwork is ongoing on the Bansi-Khesarha route for approximately 10 kilometers. The agency responsible for the project claims to complete these 10 kilometers within four months. The second phase, starting from Bansi to Bahraich, has been categorized as a special project by the Indian government and is scheduled to commence in February. This phase will involve land acquisition as well. The new rail route will include 16 stations and 12 halts. Additionally, two bridges will be constructed over the Rapti River in Shravasti.
Khalilabad se Bahraich tak Shravasti wali rail line ka phase 2 new year mein start hoga. Pehle phase mein land acquisition hoga. Sarkar ne ise special project declare kiya hai, toh budget mein koi problem nahi aayega. Pura project do phase mein complete hoga. Pehle phase mein Khalilabad se Bansi tak...
more... ka kaam almost complete ho chuka hai. Bansi-Khesarha route pe 10 kilometer tak stone blasting aur earthwork chal raha hai. Project agency ka claim hai ki yeh 10 kilometer 4 months mein complete ho jaayega. Phase 2 mein Bansi se Bahraich tak rail line ka kaam hoga. India government ne ise special project declare kiya hai, aur yeh February se start hoga. Is phase mein bhi land acquisition hoga. Is new rail route pe 16 stations aur 12 halts banenge. Shravasti mein Rapti river pe 2 bridges bhi banenge.