23/12/23, CR has successfully completed & commissioned 23.69 km new line section between Deoli-Kalamb section on Wardha-Nanded line.
CRS (Commissioner of Railway Safety) Shri. Manoj Arora inspected the new line sections & given it's safe certificate.
Speed trial of 125 kmph conducted successfully in newly opened line.
Chief Administrative Officer construction/Shri. Avanish Kumar Pandey & DRM/Nagpur Shri. Tushar Kant Pandey also conducted inspection of new line.
With this 23.69 km new line opening, CR has completed construction of 185.49 km of new lines/double line/3rd/4th lines in April-December 2023.
❇Wardha-Nanded New line (via Yavatmal-Pusad).
Nagpur div.
🔸Length- 284.65 km
🔸Overall Physical Progress- 47%
💰 Cost- ₹ 3445.48 Cr
💰 Expenditure till date- ₹ 1910.07 Crs.
🔸Funding pattern-
Railways- 60%
State govt- 40%
🔸Land acquisition completed- 1911/2138 Hectare (89%)
🔸Total stations- 26
🔸Completed stations- 4
✳Completed Section-
38.61 km.
Wardha-Kalamb.
✳In Progress Sections-
246.05 km
Kalamb-Nanded
🟢In Progress Works-
☑Earthwork- 87.54/201.14 Lcum (44%)
☑Formation- 40/284.60 km
☑Major Bridges- 32/80 completed
☑Minor Bridges- 50/320 completed
☑Road over bridge (ROB)- 43 In Progress
☑Road under bridges (RUB)- 19/52 completed
☑Station Buildings- 4/26
☑Tunnels- 6 in progress of total 8 km length
☑Track Linking- 40/284.60 km
🟠Completion of this new line will improve connectivity of Vidarbha & Marathwada region for Wardha, Yavatmal, Washim, Nanded districts.
🔘CR completed 185.50 km new line/doubling/3rd/4th line from April'23 to till date
🔘3887 Crs planned by CR in this year for new lines/doubling/3rd/4th line
🔘3006 Crs expenditure done till date (77%)
please wait...Translate to English#aAdmin #aModerator Source Cr X Handle
Please update it (1/2)
#CRInfraUpdates
Today 23/12/23, CR has successfully completed and commissioned a new 23.69 km section between Deoli-Kalamb section on the Wardha-Nanded line.
The Commissioner of Railway Safety (CRS), Shri. Manoj Arora, inspected the new line sections and gave its safe certificate.
A speed trial of 125 kmph was conducted successfully in the newly opened line.
Chief Administrative Officer construction/Shri. Avanish Kumar Pandey and DRM/Nagpur Shri. Tushar Kant Pandey also inspected the new line.
With this new 23.69 km line opening, CR has completed the construction of 185.49 km of new lines/double line/3rd/4th lines from April-December 2023.
Wardha-Nanded New line (via Yavatmal-Pusad)
Nagpur div.
-Length: 284.65 km
-Overall Physical Progress: 47%
-Cost: ₹ 3445.48 Cr
-Expenditure till date: ₹ 1910.07 Crs.
-Funding pattern:
Railways: 60%
State govt: 40%
-Land acquisition completed: 1911/2138 Hectare (89%)
-Total stations: 26
-Completed stations: 4
Completed Section:
38.61 km.
Wardha-Kalamb.
In Progress Sections:
246.05 km
Kalamb-Nanded
In Progress Works:
-Earthwork: 87.54/201.14 Lcum (44%)
-Formation: 40/284.60 km
-Major Bridges: 32/80 completed
-Minor Bridges: 50/320 completed
-Road over bridge (ROB): 43 In Progress
-Road under bridges (RUB): 19/52 completed
-Station Buildings: 4/26
-Tunnels: 6 in progress of total 8 km length
-Track Linking: 40/284.60 km
The completion of this new line will improve connectivity of Vidarbha & Marathwada region for Wardha, Yavatmal, Washim, Nanded districts.
CR completed 185.50 km of new line/doubling/3rd/4th line from April'23 to till date
CR planned ₹ 3887 Crs for new lines/doubling/3rd/4th line this year
₹ 3006 Crs expenditure done till date (77%)