MLN PBE GC update as of 22 Feb 2024,
1- NOC has been approved by wildlife department for cutting the trees in loop line of Mala railway station, this was the main issue of project delay.
Source:...
more... click here2- Bridge number 257 Mala River bridge is 80% ready and rest 20% will be completed by 29th Feb, This was the most difficult work as this is surrounded by PTR dense forest where tigers or leopards are seen usually.
3- TPM has started working from SG to Sandai halt near Mala bridge.
4-RE work is competed from PBE to Mala and only remaining from Mala bridge to Mala railway station.
CRS is expected in 2nd week of March
please wait...Translate to EnglishMLN PBE GC update as of 22 Feb 2024,
1- The wildlife department has finally given the green light to cut down trees at Mala railway station, which was holding up the whole project.
2- The Mala River bridge, also known as Bridge number 257, is almost done at 80% and the rest 20% will be wrapped up by 29th Feb. It's been a tough cookie due to it being in the middle of a dense forest where tigers and leopards hang out.
3- Work has commenced from SG to Sandai halt near Mala bridge.
4- The renovation work from PBE to Mala is all done, just some touch-ups needed from Mala bridge to Mala railway station. The final inspection is expected in the second week of March.
please wait...Translate to HindiMLN PBE GC update जैसा कि 22 फरवरी, 2024 को था।
1- NOC को माला रेलवे स्टेशन के लूप लाइन में पेड़ काटने के लिए वाइल्डलाइफ विभाग ने मंजूरी दे दी थी, यह प्रोजेक्ट देरी की मुख्य वजह थी।
2- ब्रिज नंबर 257 माला नदी का पुल 80% तैयार है और बाकी 20% 29 फरवरी तक पूरा किया जाएगा, यह काम सबसे मुश्किल था क्योंकि यह PTR घने जंगल से घिरा है जहां अक्सर बाघ या तेंदुए दिखाई देते हैं।
3- TPM ने स्जी से संदाई हॉल्ट के पास माला पुल तक काम शुरू कर दिया है।
4- RE काम PBE से माला तक पूरा हो गया है और केवल माला पुल से माला रेलवे स्टेशन तक बाकी है।
CRS मार्च के दूसरे सप्ताह में उम्मीद की जा रही है।