last week we asked few question s/demands/requests to swr gm and drmubl during their annual inspection visit at hpt.
1. when ru going to open hpt-kty line for passenegr train service?
ans: there are 36 unmanned lc btn hpt-kty line we requied 70-80 man power to solve the issue .work in progress (slow) .we ll complete it then go for crs .we cant assure you date of running pass train
2....
more... introduction of sbc-hpt ice?
ans :we r problem at bengaluru rly stations after completion of new pitline at bypl , one year from now .we ll try to increase train service btn hpt – bluru rly stations
3. ballari dists contributs high revenue to swr but not much contrubition from swr towards development of rly in ballari dist
ans : we r developing hpt station (renoavtion of hpt station with ministery of tourism).
4. request to extend sur-gdg pass train upto hpt
ans : right now its sinlge line btn hpt –gdg .let the doubling complete then we ll think of extension
4a. during nigth hpt-gdg line is non traffic almost all trains running towards gtl except tpty pass towards ubl ,so u can try to extend it?
ans :ur correct ,but there r goods trains running all the time btn ubl –bay . so it ll effect
5.construction of new pitline at hpt
ans:rigth now trains passing hpt r undergoing pm either at sbc or ubl depot (so rigth now pitline not requried at hpt)
6. construction of rob at lc no 85 near ananthasheshana gudi hampi road hospet
ans :there r some technical problem (space problem) so now we planned for rub instead of rob.