Prg-Ald have chances of doubling completion by next month.
As in my last blog post /blog/post/4279560
The poles for electrification of the doubled line between Ald to Prg were mostly erected, this time, I saw wiring also done fully.
Also, 300-400 metres stretch near Ald station east end which was not started ( may be due to wires from SSP coming perpendicular...
more... to the old line and passing above space for new doubled line). This time in that stretch, old military siding lines are removed, and one new line for doubling is laid, while one more new siding/loop line being laid along with electrification of all lines.
Now only, stone chips is to be thrown on newly laid tracks/sleepers and trials will start in Ald-Prg section. See pics:
Pic1&2: View of completed doubled line along with completed electrification between Ald-Prg as seen from Rambagh ROB.
Pic3: View of that stretch where no construction had started in April blog and now full doubled line is laid along with electrification, and levelling work for one more loop line/ siding in progress.