DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - Done (At IT/Itunja final touch is going on and at stations cross bars being installed)
Brackets - 57% done (Completion expected by Oct2019)
Wiring - Started on 31-Aug-2019 from MBP/Mohibullapur. From DAL/DaliGanj Junction wiring started except one patch. Wiring completed till BKT/Baksi Ka Talab (Completion expected by Nov2019)
SSP...
more... - Foundation at SD and STP completed (Completion expected by Dec2019)
OHE wire energized - Expected by end of Dec2019
CRS inspection - Expected by Jan2020
Commercial uses - Any point of time after CRS planned in Jan2020
** All provided dates are tentative.